| Raw Material Spec | Rate | Unit | Rate Per Kg/L |
|---|
| Raw Materials | Recipe % | Quty / SqFt (Kg) | Cost / SqFt | Cost / Brass |
|---|---|---|---|---|
| Colour layer raw materials total | 0.00% | 0.000 | 0.00 | 0.00 |
| Raw Materials | Recipe % | Quty / SqFt (Kg) | Cost / SqFt | Cost / Brass |
|---|---|---|---|---|
| Second layer raw materials total | 0.00% | 0.000 | 0.00 | 0.00 |
| Metric | SqFt Cost | Brass Cost |
|---|---|---|
| Paver Quantity Equivalent | 2.88 pcs | 288 pcs |
| Labour Operations Cost | ₹8.64 | ₹864.00 |
| Machine Name | Nos | Hp | Kw | Cycle (s) | Cycles/Hr | Runtime/Hr (s) | Units/Hr (kWh) |
|---|---|---|---|---|---|---|---|
| Total Power Units Consumed / Hour | 30.73 | ||||||
| Expense Categories | Cost Per Month (₹) | Cost Per SqFt (₹) | Cost Per Brass (₹) |
|---|---|---|---|
| Overhead Cost Total | ₹64,000.00 | ₹0.89 | ₹89.00 |
Cost Component Distribution
Note: Above Data is only for preparing project report and checking project feasibility. Also all the reading taken considering ideal condition for working. Actual statistic result depend on labor rate, efficiency, raw material cost and quality etc.